Use Fuzzy Hours for Your Software Task Time Estimates

Posted by robkraft on June 14, 2014

Like many software development shops, we need to provide estimates of the time required to fix each bug and add each new feature.  The primary reason for the estimates is to set expectations for when tasks will be completed and to prioritize what is to be worked on.

As an agile shop, we have tried a few scales for estimating such as:

tiny, small, medium, and large and also the Fibonacci sequence:    1, 2, 3, 5, 8

but the one we have been using for years that we like best is fuzzy hours.

We use the symbols 1,2,3, and 4 where:

  • 1 means 0 to 2 hours
  • 2 means 1 to 8 hours
  • 3 means 4 to 40 hours
  • 4 means more than 30 hours

Notice that our ranges overlap and that is what makes them fuzzy.  When an estimator feels an estimate is in a fuzzy zone it is up the estimator to pick one zone or the other based on their gut feeling.

We have also learned that the velocity for all items sized 1 and 2 are the same, and items with a size 3 take only slightly longer to reach a completed state (development, testing, quality assurance, and documentation all complete).  Items with a size of 4 take longer, but only about twice as long on average as a 3.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

 
%d bloggers like this: